Project Packages

Contract packages assigned to vendors with insurance & extension status

Pumping Station Civil Works
PKG-KR-03
Krishna Lift Irrigation Scheme
In Progress
Assigned To
L&T Construction
V-1041
Extension
Work Start
2024-06-15
Est. Completion
2026-12-30
Policy Start → Expiry
2024-06-012026-08-12Compliant
Pipeline Network — Reach 7
PKG-KR-07
Krishna Lift Irrigation Scheme
Delayed
Assigned To
Patel Engineering
V-1042
Extension
+90 days
Work Start
2024-09-01
Est. Completion
2026-06-30
Policy Start → Expiry
2024-08-202026-05-22Expiring soon
Expansion
Additional 4.2 km pipeline added (CR-12)