ExtendedNot issued
Tender overview
Assigned to
HCC Ltd.
V-1046
Work started
2023-05-20
Estimated completion
2026-04-30
Extension
+240 days
Geological surprises — TBM stuck
Scope expansion
Additional ventilation shaft (CR-19)
Parent project
Ken-Betwa River Linking
WRD · River Linking · Central
Insurance policy
Status
Not issued
Policy period
2023-05-15 → 2026-03-28
Active work without a valid policy — escalation required.