ExtendedExpired
Tender overview
Assigned to
Afcons Infrastructure
V-1043
Work started
2023-11-10
Estimated completion
2026-03-31
Extension
+120 days
Design change — gate trunnion
Scope expansion
No change in original scope
Parent project
Gosikhurd Dam — Phase II
WRD · Dam Safety · Vidarbha
Insurance policy
Status
Expired
Policy period
2023-11-01 → 2026-04-10
Active work without a valid policy — escalation required.